The horizontal pipeline should be 30 cm above the point of greatest soil freezing.
Posted: Mon Feb 10, 2025 6:23 am
Please note! When digging trenches, it is recommended to consider the places where the sockets will pass in order to make small recesses for them.
Step 2. Create a slope in the ditch towards the point where the sewerage system exits the room. Check the angle using a construction water level.
Step 3. Fill the bottom of the trenches with sand and tamp it down. The layer thickness is 10-15 cm. At this stage, the slope must also be observed.
Step 4. Lay all the pipes. It is recommended to insulate the pipes.
Slope of sewer pipes
Please note! The section of the pipeline macedonia mobile database in the foundation is mounted using a metal sleeve.
Step 5. Install vertical pipes to which drains or a toilet tee will be connected later. To do this, dig sticks or metal pins into the ground to which the pipes are fixed. The length of the vertical pipelines should be taken with a reserve. The excess will be cut off during installation of water receivers.
You might be interested in information - septic tank mole
Step 6. Install the ventilation riser. It is attached to the wall using clamps. The vertical pipe is brought out above the roof or cut off indoors and a check valve is installed on the upper opening of the riser.
Scheme of ventilation riser
Step 7. During the pouring of the floor, the drains are installed. If you plan to lay tiles on the screed, this must be taken into account when installing the water inlets. The screed must have a slope towards the drain. The tile or wood covering is laid after the concrete has dried.
Sewage drainage
Step 2. Create a slope in the ditch towards the point where the sewerage system exits the room. Check the angle using a construction water level.
Step 3. Fill the bottom of the trenches with sand and tamp it down. The layer thickness is 10-15 cm. At this stage, the slope must also be observed.
Step 4. Lay all the pipes. It is recommended to insulate the pipes.
Slope of sewer pipes
Please note! The section of the pipeline macedonia mobile database in the foundation is mounted using a metal sleeve.
Step 5. Install vertical pipes to which drains or a toilet tee will be connected later. To do this, dig sticks or metal pins into the ground to which the pipes are fixed. The length of the vertical pipelines should be taken with a reserve. The excess will be cut off during installation of water receivers.
You might be interested in information - septic tank mole
Step 6. Install the ventilation riser. It is attached to the wall using clamps. The vertical pipe is brought out above the roof or cut off indoors and a check valve is installed on the upper opening of the riser.
Scheme of ventilation riser
Step 7. During the pouring of the floor, the drains are installed. If you plan to lay tiles on the screed, this must be taken into account when installing the water inlets. The screed must have a slope towards the drain. The tile or wood covering is laid after the concrete has dried.
Sewage drainage